Change Orders: All changes to scope must be written and paid in full before execution. Unpaid balances pause the project immediately.
Cabinetry Lead Time: Semi-Custom cabinetry production can take up to 6 weeks depending on specifications and manufacturer schedules.
Contract Signing:
Secures your project & materials ordering
Cabinetry Arrival & Scheduling:
Due prior to mobilization
Substantial Completion:
Space is functional & livable
Final Completion:
All punch list items resolved
Kitchen Works LLC
→ Inquiry → Consultation → Design → Showroom → Contract (50% Deposit)
→ Demo → Roughs → Cabinets → Template → Parallel Work → Change Orders (due in full) → Countertops → Finishes (20% Substantial Completion)
Design
2–4 weeks
Pre-Build
6-8 weeks (times may vary)
Construction
4–8 weeks
Close-out
1 week
→ Cabinet Production → Scheduling Trigger (25% Progress Payment)
→ Punchlist → Clean → Handover (5% Final Payment)
Design
2–4 weeks
→ Inquiry → Consultation → Design → Showroom → Contract (50% Deposit)
Pre-Build
8 weeks
→ Cabinet Production → Scheduling Trigger (25% Progress Payment)
Construction
4–8 weeks
→ Demo → Roughs → Cabinets → Template → Parallel Work → Change Orders → Countertops → Finishes (20% Substantial Completion)
Close-out
1 week
→ Punchlist → Clean → Handover (5% Final Payment)