How Payment Works

Payment Summary

  1. Design Revisions: One round included. Additional revisions require a $500 retainer, applied to your final payment.
  2. Change Orders: All changes to scope must be written and paid in full before execution. Unpaid balances pause the project immediately.

  3. Cabinetry Lead Time: Semi-Custom cabinetry production can take up to 6 weeks depending on specifications and manufacturer schedules.

50%

Contract Signing:
Secures your project & materials ordering

25%

Cabinetry Arrival & Scheduling:
Due prior to mobilization

20%

Substantial Completion:
Space is functional & livable

5%

Final Completion:
All punch list items resolved

Kitchen Works LLC

Project Timeline

Inquiry Consultation Design Showroom Contract (50% Deposit)

Demo Roughs Cabinets Template Parallel Work Change Orders (due in full) Countertops Finishes (20% Substantial Completion)

Design

2–4 weeks

Pre-Build

6-8 weeks (times may vary)

Construction

4–8 weeks

Close-out

1 week

Cabinet Production Scheduling Trigger (25% Progress Payment)

Punchlist Clean Handover (5% Final Payment)

Design

2–4 weeks

Inquiry → Consultation → Design → Showroom → Contract (50% Deposit)

Pre-Build

8 weeks

Cabinet Production → Scheduling Trigger (25% Progress Payment)

Construction

4–8 weeks

Demo → Roughs → Cabinets → Template → Parallel Work → Change Orders → Countertops → Finishes (20% Substantial Completion)

Close-out

1 week

Punchlist → Clean → Handover (5% Final Payment)